# A-Steam Power Stations Reporting Peak for 23 MARCH 2004 / Report Date - 24 MARCH 2004 A - Steam Power Stations Power Stations Type Fuel No. of Units No. of Operating Units Units Load (MW) Total Load MW Target Load MW Remarks 1 2 3 4 5 6 Dibis Natural Gas 4 1 8 8 24 #2 stopped at 2058 NGPL; #3 FWP; #4 prog maint Baiji Fuel Oil 6 3 135 80 90 305 500 #1 & #3 prog maint; #4 synch at 1327; #5 forced outage; #6 limited to crack in furnace wall Daura Fuel Oil 4 1 70 70 180 #4 prog maint; #5 & #6 rehab South Baghdad Fuel Oil 6 2 30 30 60 200 #1, #2, #3 prog maint; #4 boiler leakage; #5 synch at 2159 Mussaibe Crude and Fuel Oil 4 2 200 225 425 860 #2 prog maint; #4 prog maint Nassirya Crude 4 2 140 140 280 600 #2 prog maint; #4 IDF defect - to be started tomorrow Najebia Natural Gas and Crude 2 1 90 90 160 #4 oil leakage to be started at 48 hrs Hartha Natural Gas and Crude 4 1 140 140 300 load flow problem Out of Service for Unscheduled Maintanence Total: 1378 2824 Out of Service for Program Maintanence/Rehab No activity Not Performing at Peak Performance # B- Gas_C-Power Stations Reporting Peak for 23 MARCH 2004 / Report Date - 24 MARCH 2004 B- Gas Power Stations C -Hydro Power Stations Power Stations No. of Units No. of Operating Units Station Load Target Load Fuel Use Remarks Power Stations No. of Units No. of Operating Units Station Load Target Load Discharge m3/Sec Gas Pressure Baiji 2 1 82 125 Gas Oil #2 stopped at 1730 test Musil Dam Main 4 4 620 600 Quds 2 2 80 160 Gas Oil 45 trucks Musil Dam reg 4 3 30 60 1100 Mosil 12 8 130 150 27 #1 rotor defect; #2 prog maint; #8 synch at 1130; #9 rotor defect; #11 HP Musil Pumping 2 1 110 0 Dibis 3 30 28 #4 rehab; #5 stopped at 2125 NGPL at 23/3; #6 stopped at 2108 NGPL at 23/3 Haditha Dam 6 4 215 160 2100 Old Mulla 12 5 61 128 430 #1 acc gear; #5 inlet valve; #6 stopped at 2025 HET; #8 VIB; #9 & #10 CT explosion; #12 needs rehab Samarra 3 3 80 55 780 New Mulla 6 5 172 173 2.9 #6 generator defet (sch 15/5) Himrin 2 2 40 21 200 Taji 7 55 #3 compressor; #7 needs rehab - no control card + NGPL Hindia 4 4 3 5 160 M. Taji 2 1 4 18 GO #2 software + NGPL Kufa 4 0 low level Daura 4 30 #2 prog maint; #3 needs rehab + NGPL Total 1098 896 Hilla 4 4 73 64 29 System Generation 77977 MWh Najaf 3 3 135 129 29 Syrian Line Generation 1405 MWh Khor 4 3 96 80 Natural Gas #2 prog maint Turkey Line Generation 1981 MWh Shuaiba 2 1 4 20 Natural Gas Total Generation 86790 MWh M. Shuaiba 2 Natural Gas System Peak Load 3609 MW Petro 4 1 10 0 Natural Gas #2 vib Syria Peak Load 60 MW M. Dibis 4 3 9 24 Natural Gas Turkey Peak Load 82 MW Mossil East 5 3 15 0 Gas Oil Fixed Gen Peak Load 266 MW Hmam/Zafranya 7 1 2 Gas Oil Total Peak Load 4017 MW Diesel 49 Gas Oil Baghdad Load 1370 MW Total 922 1186 Notes: Prepared from data submitted by D.G. Mohsin T. Hassan (1 (914) 360 6590). Edited by Electricity Commission U.S. Advisor Staff. # Peak Loads Reporting Peak for 23 MARCH 2004 / Report Date - 24 MARCH 2004 Power transferred from North to Middle 780 MW. Power transferred from South to Middle 70 MW. GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1370 28355 1181 1452 Duhok 82 1904 79 109 Naynawa 330 8495 354 485 Tamim 135 3643 152 201 Salah Aldeen 210 5165 215 267 Anbar 225 4932 206 259 Dyala 124 2605 109 139 Babil 95 2696 112 143 Kirbala 98 2265 94 113 Najaf 114 2702 113 129 Kadsya 60 1576 66 83 Wasit 95 2168 90 124 Muthana 65 1447 60 72 Nasirya 120 2792 116 131 Misan 66 1568 65 76 Basra 300 6226 259 259