DAILY POWER SYSTEM HIGHLIGHTS FOR APRIL 20, 2004 The CPA Electricity Advisor issues this report to note significant events or conditions of interest in the power sector. The basic daily data on the power system is available on the CPA web site. HIGHLIGHTS: We should begin to see a gradual climb in generation as units return from maintenance. Generation: Peak Power 3866Mw, 76,387Mw hours, 7-day Avg. 3673Mw Turkish Region Average Generation 169.5 Mw (not included in Peak Power) Generators Returned to Service: (5) 365 Mw Hartha 4 180 Mw Qudas 2 90 Mw Old Mulla 7 15 Mw New Mulla 3 30 Mw Khor Zubayr 1 50 Mw Generators Unscheduled Out of Service (19) 691 Mw PLANT Type SP, CP, RP, HP Fault Mw * Dibis 1 SP Gas Pressure Low 8 Dibis 2 SP Boiler Leak 8 * South Baghdad 5 SP Boiler leak 30 South Baghdad 6 SP Feed Water pump 30 * Mussaibe 4 SP Drum Level low 200 Baiji 1 CP Filter Cleaning 85 Baiji Mobile, 4 CP No Fuel Filters 100 Khor Zubayr 4 CP Flame loss 50 Mosil 1 CP Rotor Defect 15 Mosil 2 CP Load Gear Oil leak 15 * Mosil 8 CP Reverse Power 15 Mosil 9 CP Rotor Defect 15 Old Mulla 6 CP High exhaust temperature 15 Old Mulla 9 CP Load gear problems 15 Old Mulla 10 CP Vibrations 15 New Mulla 4 CP Load gear oil leak 30 Taji 3, CP Compressor 15 Taji 5 CP Excitor problem 15 M. Taji 2 CP Software 15 RED – Denotes out of service since last report Generators Scheduled Out of Service (25) 1438 Mw PLANT Type SP/NG Prog. Maintenance(M) / Rehab (R) Maint. Org. Date out-of -service Est. In-service Date Mw Baiji 1 SP M TBD 21 Mar 04 15 May 100 Baiji 3 SP M Bechtel 29 Feb 04 20 Apr 100 Dibis 4 SP M ME 15 Mar 04 30 Apr 8 Doura 4 CP M ME 14 Apr 04 TBD 20 Doura 3 CP R GRD/RIE 1 Mar 03 TBD 20 Doura 3 SP M ME 18 Mar 04 18 May 65 Doura 4 SP M ME 2 Feb 04 20 Apr 65 Doura 5 SP R Bechtel Jul 03 20 Jun 100 Doura 6 SP R Bechtel Jul 03 20 Jul 100 Dibis 4 CP R GRD/RIE Sep 03 12 May 30 Hartha 1 SP M ME 22 Mar 04 23 May 100 Khor Zubayr 2 CP R GRD/RIE 15 Mar 04 15 Jun 50 Mussaibe 2 SP M ME 28 Feb 04 28 Apr 200 Nassirya 1 SP M ME 30 Mar 04 15 May 130 Nassirya 2 SP M ME 9 Mar 04 15 Apr 150 New Mulla 6 CP R GRD/RIE 28 Mar 04 15 May 30 Old Mulla CP M ME 17 Apr 04 TBD 15 Old Mulla 2 CP M ME 17 Apr 04 TBD 15 Old Mulla 8 CP M ME 17 Apr 04 TBD 15 Old Mulla 12 CP R GRD/RIE 1 Oct 03 15 May 15 South Baghdad 1 SP M (Awaiting parts) ME 12 Feb 04 12 Apr 30 South Baghdad 2 SP M (Awaiting Parts) ME 12 Feb 04 12 Apr 30 South Baghdad 3 SP R ME 18 Mar 04 18 May 20 Taji 7 CP R GRD/RIE 1 Oct 03 15 May 15 Taji 6 CP M ME 2 Apr 04 TBD 15 LEGEND OF ELECTRICAL SYSTEM POWER SOURCE SP: STEAM POWER – These plants use either fuel oil or crude in burners CP: COMBUSTION POWER RP: RECIPROCATING POWER HP: HYDRO POWER Transmission: LINE Kv Fault Maint. Org. Date out-of -service Est. In-service Date Comments Nassiriya-Khor Zubayr 400 Sabotage Bechtel 26 May 102 towers complete/212req’d Haditha-Baghd West 400 Sabotage GRD/RIE Loading 246 towers complete/246 req’d Hartha-Qut – Wasit 400 Sabotage GRD/RIE Complete MoE completing PLC work Baiji - Baghd West #1 400 Sabotage GRD/RIE Complete Operational Baghd E.-Baghd S. #2 400 New Line GRD/RIE Complete 81 towers complete/81req’d Haditha – Qaim 400 Sabotage GRD-RIE TBD No contract awarded Baiji – Haditha 400 Sabotage Bechtel TBD No contract awarded Diyala Connection 400 New Line ME 15 Jun Dibis/Erbil-Qara Qosh 132 New Line GRD/RIE 15 May Contractor mobilized Dibis to Old Kirkuk 132 Reconductor GRD-RIE 15 Jun Bids for work under evaluation Mosul – Mosul East 132 Sabotage ME TBD Shuwaiba-Toba-Hamar 132 Sabotage ME Complete 44 towers complete/44 req’d Samediya – New Baghdad 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Jazair to Yarmook 132 Reconductor GRD-RIE 15 Jun Contract Awarded 24 Mar Baghd West – Jamia 132 Sabotage ME TBD Al Amarah-Burzulgan 132 Looting GRD-RIE 15 Jun 26 towers complete /126 req’d Temim- Tuz 132 Sabotage ME TBD Nejibiya – Hartha 132 Sabotage ME TBD Lines Returned to service: Distribution: Power transferred from North to Middle 775 MW. Power transferred from South to Middle 35 MW. GOVERNORATE Peak Load MW MWH Average Load MW Demand Load MW Baghdad 1190 23523 980 1425 Duhok 80 1909 80 112 Naynawa 365 7707 321 522 Tamim 135 3204 134 194 Salah Aldeen 220 4737 197 261 Anbar 195 4194 175 234 Dyala 105 2050 85 143 Babil 100 2251 94 150 Kirbala 97 2011 84 104 Najaf 118 2477 103 103 Kadsya 79 1520 63 89 Wasit 100 1993 83 128 Muthana 65 1363 57 77 Nasirya 121 2657 111 126 Misan 65 1518 63 84 Basra 240 5388 225 265 Data compiled and reported by: LTC Tharnell M. Thomas CENTCOM LNO CPA Ministry of Electricity thomast2orha.centcom.mil Page PAGE 1 of NUMPAGES 3